Minimum Completion Time for DAG Dependencies

Amazon logoAmazon● MediumNEW GRADFULLTIMEPHONE SCREENONSITE INTERVIEW

Problem statement

Each task has a positive duration. A dependency [before,after] means task after may start only after task before finishes. The dependency graph is acyclic.

The problem statement continues
Pro

Examples

Example 1

durations = [3,2,5]dependencies = [[0,2],[1,2]]return = 8

Tasks 0 and 1 run together; task 2 then finishes at time 8.

FastPrep Pro
Reported in 1 Amazon interview this week

Unlock this recently reported problem

FastPrep Pro gives you full access to interview problems reported within the last week.

  • Full problem statement and constraints
  • 2 more worked examples, explained
  • Guided hints and editorial
  • Run your code on real test cases
$8.25/month

$99 billed yearly — or $19 month-to-month. Cancel anytime.

Free plan — 2 of 2 free unlocks used this week
See Amazon hiring insights
CodePython 3
Run and Submit unlock with Pro
FastPrep Pro
Reported in 1 Amazon interview this week

Unlock this recently reported problem

FastPrep Pro gives you full access to interview problems reported within the last week.

  • Full problem statement and constraints
  • 2 more worked examples, explained
  • Guided hints and editorial
  • Run your code on real test cases
$8.25/month

$99 billed yearly — or $19 month-to-month. Cancel anytime.

Free plan — 2 of 2 free unlocks used this week